|
(Clinical)
Trials and (Regulatory)Tribulations
Unless
the regulatory system of India rise to the occasion by being transparent
and efficient, the country shall fail to seize the opportunities
in clinical trials, says Dr Arun D Bhatt
In
recent years, Indias potential as a major hub of international
clinical has been recognised. The advantages of large patient pool
of treatment-naive patients, well-trained investigators and reduced
trial costs have made international pharmaceutical companies and
contract research organisations (CROs) look at India favourably.
In a regulatory situation where it takes 10-15 years and $500 million
to develop one new drug, each days delay in obtaining an approval
can result in a loss of over $1.5 million for the sponsor. Hence,
their major requirement is rapid initiation and timely completion
of clinical trial. One of the biggest hurdles in the clinical trial
plans is uncertainty and time to obtain regulatory permissions.
If the regulatory system of a country is not transparent and efficient,
the international trials will go to other countries. Is our regulatory
system responsive to this need?
Regulations
in developing countries
A
review undertaken by the Association of the British Pharmaceutical
Industry in 2000 showed that most European countries have a two-step
process for clinical trial permission -- Ethics Committee (EC) review
and Health Authority (HA) review. (Table 1). Some countries require
EC approval prior to HA approval while some others permit parallel
processing of clinical trial application by both. The range of time
for EC approval varies from two weeks in Finland to 12 weeks in
UK and time for HA approval ranges from five days in Australia to
60 days in Italy. The overall time for both EC and HA approval ranges
from 6-12 weeks. In France and Belgium there is no formal HA approval.
In these countries, a sponsor after obtaining EC approval can initiate
trial after notifying the HA with a letter of intent.
The
UK has four-step process with a total time of 10-12 weeks for approval
and is considered one of the slowest countries in Europe and world.
There are concerns that UK is losing her competitive edge because
of a slow clinical trial approval process.
In
USA, an Investigational New Drug (IND) application goes into effect
30 days after FDA receives the IND, unless FDA notifies the sponsor
that the investigations described in the IND are subject to a clinical
hold. The IND can also begin earlier than 30 days, if FDA notifies
the sponsor that the clinical investigation in the IND may begin.
Situation
in Asia
| Regulatory
and Ethical Review Time in Developed Countries |
|
Country
|
Time
for Regulatory Approval
|
Time
for EC Approval
|
Time
for All Approval
|
|
Australia
|
5
days
|
6-8
weeks
|
10
weeks
|
|
Belgium
|
Notification
only
|
6
weeks
|
6
weeks
|
|
Denmark
|
4-6
days
|
8
weeks
|
8
weeks
|
|
Finland
|
60
days
|
2
weeks
|
8-10
weeks
|
|
France
|
Notification
only
|
8
weeks
|
8
weeks
|
|
Germany
|
2
weeks
|
10
weeks
|
12
weeks
|
|
Israel
|
45
days
|
6
weeks
|
12
weeks
|
|
Italy
|
60
days
|
60-120
days
|
8-12
weeks
|
|
Netherlands
|
1
month
|
2-3
months
|
3
months
|
|
Norway
|
6
weeks
|
4
weeks
|
6
weeks
|
|
Poland
|
42
days
|
6
weeks
|
10
weeks
|
|
South
Africa
|
6-12
weeks
|
4-6
weeks
|
6-12
weeks
|
|
Spain
|
2
months
|
4-12
weeks
|
12
weeks
|
|
Sweden
|
6-10
weeks
|
4-6
weeks
|
6-10
weeks
|
|
UK
|
35
days
|
10-12
weeks
|
10-12
weeks
|
|
Table
I
|
In
most Asian countries (Table 2), HA and Institutional Review Board
(IRB) approval for protocol takes about three months. It is usual
to obtain IRB approval followed by HA approval, a process that usually
slows timelines. In Singapore this sequential process takes only
three months. Philippines, Indonesia, Taiwan and Malaysia allow
parallel submission to IRB and HA. However, the HA approval is dependent
on IRB approval. Until recently, the protocol approval in Taiwan
could take longer than six months. Taiwan has made significant efforts
to reduce the time for protocol approval to attract international
clinical trials.
Indian
scenario
No
official Indian survey of time for HA approval is available. Informal
discussions with sponsors and CROs suggest a range from 4-6 months.
Some claim to obtain approval in two months time. However, such
short timelines are exceptions. Sometimes an international MNC turns
to India, when the global trial is close to completion and it has
not been able to recruit adequate number of patients. The challenge
for the local subsidiary is to recruit patients within a short time
of 4-6 months. As the HA timelines in our country are longer and
unpredictable, the local subsidiary is unable to accept such a project.
This means a loss of opportunity for India to participate in international
trial!
The
companies embarking on new drug research have complained about delays
in getting approval for phase I. The timelines for approval have
been 5-8 months or longer. In a world where international competition
can get a phase I approval from USFDA in just 30 days, such delays
are costly for these Indian companies! Most of the sponsors are
concerned about uncertainty of the timelines, as it could take much
longer than six months. There are hardly any technical queries from
HA authorities on the protocol.
Most
often the applicant receives some administrative queries or is asked
to fulfil new requirements that are not part of Schedule Y or any
other regulatory guidelines. If the HA authorities seek opinion
of external experts or ICMR on the protocol, the timelines become
much longer and unpredictable. The applicant dreads this scenario
and makes all efforts to avoid this situation!
In
1999, the Pharmaceutical Research and Development Committee headed
by Dr Mashelkar commented on this issue as follows:
Applications
submitted to the DCG(I) for permission for clinical trials in respect
of new drug applications (NDA) and abbreviated new drug applications
(ANDA) are often referred to outside agencies like the Indian Council
of Medical Research (ICMR) and the Department of Biotechnology,
Government of India (DBT) for review. This arrangement often leaves
very little control with regard to the time runs.
| Country |
Time
in
months
|
| China |
6
|
| Hong
Kong |
3 |
| Indonesia |
3
|
| Korea |
3-6
|
| Malaysia |
3-4
|
| Philippines |
3
|
| Singapore |
3 |
| Taiwan |
3 |
| Thailand
|
3-6
|
Besides
HA approval, the international applicant also needs licence to import
clinical trial samples and permission from Directorate General of
Foreign Trade to export blood samples for analysis to a central
laboratory. The EC approval can take from 1-3 months. However, some
ECs review the application only after the HA permission is given.
This means that a clinical trial can start in India almost 7-9 months
after the protocol is submitted to HA and EC. This is criminal waste
of time as globally acceptable approval time for clinical trials
is just 3 months! Our regulatory system needs to change to meet
this goal!
Potential
long term solutions
There
is a need to bring Indian regulatory system in line with international
agencies. The Pharmaceutical Research and Development Committee
has made several recommendations in 1999 to revamp the regulatory
system. Some of the recommendations are:
-
In order that the applicant is enabled to complete the investigations
in the shortest possible time, it is imperative that adequate
infrastructure for fast track clearances is created in the Central
Drugs Standard Control Organisation (CDSCO).
-
CDSCO is required to carry out multifarious functions but expertise
in technical, administrative and vigilance functions is not sufficient.
Full-time experts must be there with CDSCO for timely evaluation
of the papers submitted by the parties
-
The DCG(I) should have under his direct supervision a number of
divisions/departments with officers and support staff adequate
and competent for the job
-
Full-time experts in key areas with adequate scientific and medical
expertise and back-up support should be made available to the
DCGI
-
Responsibility and accountability for the decisions and their
timeliness must rest on the shoulders of the DCG(I) and/or the
divisional or departmental heads
-
On a priority basis, the office of the DCGI should be provided
with electronic networking nationally and internationally to facilitate
and expedite decisions
-
A time schedule for processing of application for different stages
of clinical trials should be developed and made known by the DCGI
along with the fees to be charged for different stages. Most HA
in Asia have their own website and information regarding their
policies and guidelines are available electronically. In contrast
there is no website providing access to our regulatory agency!
The
committee recommended a time-frame of one year to revamp and modernise
the CDSCO. In spite of above recommendations, there does not seem
to much progress in the direction of making our regulatory system
efficient and transparent!
Alternative
strategy
The
above changes are desirable but are unlikely to happen in near future.
There is a need for an alternative regulatory process to approve
the clinical trials in a reasonable time of three months or less.
In Asia, Taiwan and Malaysia have improved their HA system to complete
the approvals in three months time. Our HA authorities can follow
the system in other Asian countries and developed nations. The sponsor
should submit the clinical trial protocol with approval letter of
1 EC. Based on this, the HA authorities could give their approval
in two weeks. With this approach, the overall process of protocol
approval is unlikely to exceed three months. This will make India
an attractive country for clinical trials!
The
Dream From Report of the Pharmaceutical Research and Development
Committee, 1999: Heres what the Economist may write on August
15th 2004 on Indias remarkable turn around Regulatory framework,
The most spectacular development has been the establishment
of a professionally managed and transparent regulatory framework
that competes in processing time with the best in the world.
A
grand new steel and glass building heavily populated by computers
gets approvals moving quickly and efficiently. The approval time
has recorded a remarkable fall in the no of days to approval from
two years to 30 days.
Will
this dream (of efficient regulatory system) be fulfilled or the
current nightmare (of regulatory unpredictability) will continue?
The
writer is consultant, Pharmaceutical Medicine & Clinical Pharmacology.
Email: arundbhatt@hotmail.com
|